BJC MBMC Incremental CT

Fire Solutions provided updates to the fire suppression systems by adding and relocating fire sprinklers from the existing fire sprinkler system to provide proper coverage for the architectural changes. White standard coverage quick response concealor fire sprinkler heads were installed in all ceilings to match the existing fire sprinkler heads. All design, material, fabrication and installation was done per NFPA 13. Fire Solutions was responsible for obtaining the necessary permits for the work. The new arm-overs, drops and/or sprigs installed were black schedule 40 threaded pipe and fittings.

Project Details

Location

St. Louis, MO

Client

Barnes Jewish Christian

Project Type

Healthcare

Contractor

Interface Construction Corporation