Northpark Warehouse

Fire Solutions was recruited by Clayco to provide fire protection for the new 538,000-square foot Northpark Warehouse in Berkeley, MO.

Services provided included: design, fabrication, and installation of fourteen (14) K-17 ESFR automatic sprinkler systems which detailed 5,618-sprinkler heads, installation of double check back-flow preventer, design and installation of one (1) electric fire pump rated 120-psi @1500-GPM which included a jockey pump, jockey pump controller and wye-delta open reduced voltage controller. All work, including excavation, backfill, material, and installation of exterior 10” site fire loop including seven (7) lead-ins and eleven (11) fire hydrants, was completed on-schedule and in compliance with NFPA 13 standards.

Project Details

Location

Berkeley, MO

Client

Clayco

Project Type

Industrial / Warehouse

Contractor

Clayco

Northpark Warehouse 1